Bing tracking

May 22, 2017: Then and now

Construction, May 2016
Laying the groundwork in May, 2016
May 22, 2017
Progressing toward the finish line in May, 2017

 

 

 

 

 

 

 

 

 

 

Last May, the building crews for the Hagfors Center were just beginning to break ground and lay basic foundations. This side-by-side comparison of the construction site from last year to this year shows how much progress can be made in twelve short months. Read below to learn more about last week’s highlights and this week’s priorities.

Construction Site Work

  • Closure of 21st Avenue South; restricted parking in Lot A. In order to accommodate the next phase of construction, a portion of 21st Avenue South and South 7th Street are now closed to pedestrian and street traffic through the summer. Pedestrians are still able to cross 21st Avenue South to access Anderson and Luther residence halls to the south of the construction site; and vehicles can still
    Concrete bench seating, May 22, 2017
    The concrete bench seating is almost complete.

    access South 8th Street and the parking lots south of it. Vehicles and pedestrians are able to use the north end of 21st Avenue South to access Riverside Avenue, South 6th Street, the driveway adjacent to Oren Gateway Center, and the private home south of Oren. Augsburg also has designated Lot A as construction-related parking only. Special permits are required to park in that lot.

  • Seating. The site’s three, gray-toned, concrete benches took form last week (pictured, right) after being formed and poured. Crews will now focus on backfilling and leveling the ground around the perimeter of the curved structures.
  • Glass Art Installation, May 22, 2017
    Teri Kwant’s artwork has created a new lens through which to see campus and downtown Minneapolis.

    Sidewalks. Crews are continuing to develop the walkways along the east side of the building and 7th Street this week by forming and pouring the concrete for sidewalks (weather permitting).

  • Skyway. Artist Teri Kwant’s glass art instillation was finally set in place and now offers a uniquely layered perspective of downtown for those passing through (pictured, right). Now that the artistic glass has been set, work can begin on sealing up the skyway – which will start with installation of the spray foam at the head of the skyway.
  • Main entrance. Crews are beginning to install the window system flanking the center’s west entrance.
  • Main lobby. Recessed lighting was installed and strategically positioned to illuminate the elm walls in the lobby while shade pockets in the learning commons and main lobby are being placed along the windows (see design, bottom right).

    Rendering of lights, May 22, 2017
    The recessed lighting pictured on the ceiling of this design were aimed to highlight the feature wall last week.
  • Basement flooring. The installation of a few colors of flooring for the building’s basement level began and will continue through this week. The flooring includes colored rubber at classroom and lab entry alcoves that coordinates with the color of the exterior fins (pictured, bottom left).

    Basement flooring, May 22, 2017
    Rubber and concrete flooring have been installed in the basement and science labs.